Recent Projects

Underground Piping Replacement

The project consisted of removal and blind flange of approximately 300' of steam piping, both 8" and 4".  Supply new perma-pipe for direct burial and install after environmental cleanup.


Perma-pipe
Perma-pipe installation
Perma-pipe
Perma-pipe

Reheat Piping Modification / Inspection

A 20" major steam line valve recently required repairs.  Unfortunately, due to the location of the valve and timing issues, access could only be obtained by removing a section of the piping followed by repairs and rewelding


Access hole cut out and subsequently repaired
Reheat Piping - removal of access hole for repair
Fit up for welding of access area
Reheat Piping - fit up for replacement of access hole area
Magnetic particle testing revealed a linear indication that was repaired - indication is in center of photo on weld
Reheat Piping - magnetic particle indication of repair weld found in the root pass
Final repair weld
Reheat Piping - final repair weld

Boiler Feed Discharge Piping Replacement

OST Services provided welding and fitting services to replace approximately 60' of piping and fittings with the boiler feed pump discharge.  The work was performed on a quick turn basis to avoid unnecessary down time at the production facility.


Condition Assessment of Boiler Tubing

An assessment of the boiler tube conditions was performed using a remote field testing (RFT) procedure.  RFT represents a nondestructive, volumetric inspection technique capable of detecting variations in the tube wall thickness.  This procedure utilizes a a single channel inspection probe, coupled to a Russel Ferroscope model 204 instrument.  Signal output is processed, stored, and analyzed on an external laptop computer

 


Boiler tubing - condition assesment